2026-10-14 note at TB
The ship You'll Thank Me Later arrived back at the Cape from Starbase carrying Starship hardware.
-
2026-10-14 transport 4PL (four point lifter) from SAN to MB2
The 4PL used for ship lifts moved from Sanchez into Mega Bay 2 and hoisted from its stand.
-
2026-10-14 identify hardware 4PL (four point lifter)
The 4PL used for ship lifts moved from Sanchez into Mega Bay 2 and hoisted from its stand.
-
2026-10-14 UNCONFIRMED note at MAS2
Aerial view of construction progress at the Massey's #2 site.
-
2026-10-14 UNCONFIRMED note at MAS
Massey's is being cleared ahead of testing. Rough Riders asks whether Booster 23 is next; that is a question, not a confirmation.
-
2026-10-14 roll B24 LOX-landing-tank from SFC to MB1
Booster 24 LOX landing tank took a long route from Starfactory into Mega Bay 1 for installation.
-
2026-10-14 UNCONFIRMED identify site Massey's #2 site
RGV Aerial Photography shows the Massey's #2 site under construction.
-
2026-10-13 other S43.1 at MAS
S43.1 tested inside the Supercrusher at Massey's overnight.
-
2026-10-13 note at GB-TX about gigabay-bridge-crane
More bridge crane testing inside Gigabay.
-
2026-10-13 identify hardware Gigabay bridge crane
More bridge crane testing inside Gigabay.
-
2026-10-13 transport B23 from MB1 to MAS
Booster 23 rolled from the production site to Massey's for its initial cryo proof testing.
-
2026-10-12 lift B23 to MB1
Booster 23 lifted onto the booster cryo / thrust sim stand.
-
2026-10-12 lift S40 to MB2
Ship 40 broken over and lifted vertical inside Mega Bay 2, its first tip-up since recovery, using two cranes and the SHT-SAF.
-
2026-10-11 note at GB-TX about gigabay-bridge-crane
Gigabay large bridge crane received its working load limit sign: 420.
-
2026-10-11 identify hardware Gigabay bridge crane
Gigabay large bridge crane received its working load limit sign: 420.
-
2026-10-10 transport S40 from PoB to SAN
Ship 40 offloaded from Forte and rolled overnight from the Port of Brownsville to the production site.
-
2026-10-10 transport S42 from MAS to MB2
Ship 42 returned to Mega Bay 2 after its third round of testing at Massey's.
-
2026-10-09 cryo S42 at MAS
Ship 42 frosted on both tanks during cryo testing.
-
2026-10-09 transport S42 from MB2 to MAS
Ship 42 rolled to Massey's on the ship cryo stand after all 6 engines were removed.
-
2026-10-08 UNCONFIRMED Flight 16 (Starlink 30-1) F16 NET 2026-12-10 at 39A
CADENA advisory: Flight 15 from Starbase Pad 2 NET 8 Nov 2026; Flight 16 (Starlink 30-1), potentially LC-39A, NET 10 Dec 2026.
-
2026-10-08 UNCONFIRMED Flight 15 F15 NET 2026-11-08 at P2
CADENA advisory: Flight 15 from Starbase Pad 2 NET 8 Nov 2026; Flight 16 (Starlink 30-1), potentially LC-39A, NET 10 Dec 2026.
-
2026-10-08 transport OG can crusher to MAS
The original can crusher moved to Massey's.
-
2026-10-08 identify hardware OG can crusher
The original can crusher moved to Massey's.
-
2026-10-08 roll B24 transfer-tube from SFC to MB1
Booster 24 full transfer tube rolled into Mega Bay 1.
-
2026-10-07 transport S40 from SEA to PoB
Ship 40 arrived at the Port of Brownsville aboard Forte, 75 days after its Indian Ocean splashdown.
-
2026-10-07 roll B24 CH4-landing-tank from SFC to MB1
Booster 24 methane landing tank and lower transfer tube rolled from Starfactory to Mega Bay 1.
-
2026-10-07 roll B24 A6:4 from SFC to MB1
Booster 24 A6:4 rolled from Starfactory to Mega Bay 1.
-
2026-10-06 UNCONFIRMED cryo BLT-TA at MAS
Booster landing tank test article appeared to burst near its base during a cryo test, spilling liquid nitrogen. Intentional or not is unconfirmed.
-
2026-10-05 roll S44 A2:4 to MB2
Ship 44 A2:4 rolled into Mega Bay 2.
-
2026-10-04 transport S39.1 to MAS
S39.1 rolled from the production site back to Massey's. Reason unclear.
-
2026-10-02 roll B24 A5:4 from SFC to MB1
Booster 24 A5:4 rolled from Starfactory to Mega Bay 1. Initially misidentified as A6.
-
2026-09-05 transport Booster workstand, SHT ship aft frame from RR to TB
A new booster workstand for Gigabay and a Starship Horizontal Transport Ship Aft Frame moved from Roberts Road to the KSC Turn Basin, to ship to Starbase.
-
2026-09-05 identify hardware SHT ship aft frame
A new booster workstand for Gigabay and a Starship Horizontal Transport Ship Aft Frame moved from Roberts Road to the KSC Turn Basin, to ship to Starbase.
-
2026-09-05 identify hardware Booster workstand
A new booster workstand for Gigabay and a Starship Horizontal Transport Ship Aft Frame moved from Roberts Road to the KSC Turn Basin, to ship to Starbase.
-
2026-09-03 note at 39A
Artemis III crew visit the Starship launch tower at LC-39A.
-
2026-09-01 stack S44 Nosecone at SFC
Reported by 1 Sep 2026: Ship 44 nosecone TPS work complete, forward flaps installed, and the nosecone stacked onto the payload bay in Starfactory.